Mix, Bechtel: Five ministers alternated when I was in charge of works on Transilvania motorway
Ziarul Financiar
16.11.2009
Michael Mix, project manager of Transilvania Motorway, who
will end his term in Romania at the beginning of December, says the
slow pace of completion of the first 42 kilometres had to do in
part with the numerous changes that occurred within the Ministry of
Transportation, as well as to the last plot being expropriated as
late as in August this year. "The project targeted the construction
of 170 km of motorway by 2008, but there were a lot of changes in a
relatively short period of time. During my term, five
transportation ministers alternated, eight directors of CNADNR
(National Company for Motorways and National Roads) were changed,
as were ten project managers," Mix, told ZF in an interview. His
term ends on December 2nd, after the first 42 km of the motorway,
on the 2B section (Campia Turzii - Cluj Vest) are inaugurated.
He
will be replaced by Mike Swinford, currently project manager of the
motorway that Bechtel is building in Albania. Asked if he was not
disappointed about what he achieved during his term, Mix said: "I
don't see things this way, because we managed to develop a project
and speed up works to the point where Romanians can see the
results."